Please note all photos can be enlarged by
clicking on!!
|
|
|
|
|
|

2 days in and Peter has transformed the
garden!
|
|

new steps are hewn out of the bank
|

circular paving arrive and stacked for use
|

The hardwood sleepers have arrived
|

Footings dug out
|

footings mass filled with concrete
|

materials are being stacked for next week!
|

A view looking down!
|

and again, showing all roughly dug out!
|

steps are well under way!
|

working upwards
|

steps constructed securely one at a time!
|

each with a swept brick riser
|

Each slab has to be cut to fit!
|

The main steps are really beginning to take
shape!
|

The upper platform is being marked out!
|

All has to be made to fit perfectly!
|

Peter is now 2 weeks into this project
|

a lot of work has gone into these steps!
|

Monday and slabs are fixed
|

working down
|

Peter secures each slab.
|

Marc & Richard bring in more sleepers
|

electric cabling is going in...
|

Peter has pointed the steps....
|

Richard & Marc start the lower level
|

corner sleepers go in...
|

Peter starts the lower wall..
|

I just had to look down again!
|

Wednesday and Peter continues with the walling...
|

This will retain part of the bank behind...
|
|

line of upright supports continue...
|

each set in wet concrete.
|

The wall sweeps upwards!
|

Remaining upright sleepers are set in today
Thursday...
|

Sleepers on the way down! They are heavy!
|

Peter has put in the headers..
|

Here will be a set of sleeper steps.
|

Friday and the sleeper wall goes in!
|

Peter & Richard break for tea!!!
|
more to follow in the next
few days....
this is up to Friday eve
19/09/03.
We are now 3 weeks into
this project...
|

Monday and being graded out!
|

Peter cotinues with the brickwork
|

Again sweeping down!!
|

Rear right corner is being sorted...
|

Rear sleepers are secured
|

Sleeper steps are roughly placed
|

Tuesday evening......
|

Sleeper steps are secured firm
|

3pm, Peter & Richard exhausted after
all the lifting!
|

Each sleeper step is drilled and pinned
|
|

End of Wednesday and grading out of the
lower steps
|

The steps go up!
|

Extra risers needed! We had to double up!
|

These steps have proved a lot more difficult
|

than I had imagined! A lot of awkward cutting!
|
These sleeper steps have
taken Peter & Richard 3 days to build!! These have proved much harder
than I expected! A couple of our other men were involved as well in some
of the lifting and shifting of these very heavy hardwood sleepers! |

Peter has started on the retaining walls
on Friday
|

Monday and sleeper wall is secured!
|

Ready almost for planting!
|

Other side is started, awaiting sleeper
delivery Tuesday!
|

Steps being tidied and firmed..
|
|

brick circle goes in
|

sub base for paving
|

fine grading!
|

The view up has changed!
|

Gently sweeping lower right...Tues eve
|

Large truck load of well rotted horse manure
was added to the beds today Wednesday!
|

We are still being delayed awaiting for
the very late arrival of railway sleepers ordered for Tuesday from Builder
Centre!
|

Steps nicely finished!
|

upper terrace laid & jointed
|
|

Stepping stones in, steps mulched
|

Planting begins
|

Hilary was with us today Friday!
|

Sorry Hilary!!
|
|

Planting to be completed next Monday...
|

Now Monday. Tim caught on camera!
|

Much of the planting
|

has been completed by Hilary today
|

Peter, Marc and Tim have been
|

putting in the finishing touches
|

to the hard landscaping.
|

Stepping stones in
|

Gravel placed
|

All blends together!
|

End of Monday. Looks really good!
|

Tuesday and the turf goes down...
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
We tidied and left
on Wed 8th Oct |
|
|
|
|